Solicitation Number: 70Z085Q11258
Date Added: March 01, 2025
General Requirements
Intent. This standard specification invokes general requirements for conducting vessel repairs performed by commercial contractors at a Coast Guard facility for Coast Guard vessels.
COAST GUARD DRAWINGS
Coast Guard Drawing 418A-WMSL-100-001, Rev B, General Arrangements
Coast Guard Drawing 418A-WMSL-801-001, Rev A, Booklet of General Plans
Coast Guard Drawing 750-WMSL-436-011, Rev E, Fire Detection Sys Deck Plan (ASC436009)
Coast Guard Drawing 750-WMSL-436-013, Rev C, Fire Detection Sys Cable Running Sheets (ASC436010)
Coast Guard Drawing 750-WMSL-436-014, Rev -, Fire Detection and Control System Schematic (ASC436028)
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements
Surface Forces Logistics Center Standard Specification 3041 (SFLC Std Spec 3041), 2022, Shipboard Electrical Cable Test
Surface Forces Logistics Center Standard Specification 3042 (SFLC Std Spec 3042), 2022, Shipboard Electrical Cable Removal, Relocation, Splice, Repair, and Installation
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022, Requirements for Preservation of Ship Structures
Coast Guard Technical Publication (TP) 9919, SWBS 436, Feb 2022, Fire and Smoke Detection System (For Hull 757)
OTHER REFERENCES
National Fire Protection Association (NFPA) 72, 2022 Edition, National Fire Alarm and Signaling Code
3. REQUIREMENTS
3.1 General. The Contractor must conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability. The requirements of this WI apply to all work under the scope of this contract, whether explicitly stated in all following work items or not, and to all other work subsequently authorized by changes, modifications, or extensions to the contract.
3.2 Materials. The Contractor must obtain all of the materials required to complete this job with the exception of the Government-furnished Property shown in Paragraph 1.2 of Work Item.
3.3. Period of Performance. The period of performance window for this work starts on 09 April 2025 and ends on 01 July 2025.
3.4. Location. The Contractor must perform the work while the USCGC MIDGETT (WMSL 757) is alongside the pier on 400 Sand Island Pkwy Honolulu, HI 96819-4326.
58300_RTK_1023_418
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to perform Biennial Maintenance on Dual Point Davit listed in Table 1.
TABLE 1 – DUAL POINT DAVIT NAMEPLATE DATA
description
LOCATION
davit total gross weight
Allied Systems Dual Point Davit with Control Console
Models: DDP11000CTS & SP2200
Weather Deck, STBD Side, Frame 47
29,000 lbs
1.2 Government-furnished property.
MTI
ITEM DESCRIPTION
NSN/PN
QTY
ESTIMATED COST ($/UNIT)
Y
CB-OTH Mark IV
(Coast Guard Drawing 26B-CB-IV-801-001)
N/A
1 ea.
N/A
Y
Hook
Model APR-356-CBH
2 ea.
5000.00
2. REFERENCES
Coast Guard Drawings
Coast Guard Drawing 418A-WMSL-100-001, Rev B, General Arrangements
Coast Guard Drawing 418A-WMSL-801-001 Rev A, Booklet of General Plan
COAST GUARD PUBLICATIONS
Coast Guard Technical Publication (TP) LR-H5-0002-V0, SWBS 583, Oct 2023, Boat Davit - Models DDP11000CTS & SP2200 (Hull 757)
Coast Guard Technical Publication (TP) 9618, S
Set-Aside: Total Small Business Set-Aside (FAR 19.5) (SBA)
Place of Performance: Honolulu, Hawaii, UNITED STATES
NAICS Codes:
336611
Files:
SAM.gov
Sep 14, 2026 Active