app.rfpplanner.com

Opportunity Details

Solicitation Number: 70Z085Q250002226

Date Added: February 04, 2025

Description:

This is to be awarded lowest price technically acceptable

General Requirements 

1. SCOPE  

1.1 Intent. This standard specification invokes general requirements for conducting vessel repairs performed by commercial contractors at a Coast Guard facility for Coast Guard vessels.  

 
2. REFERENCES  

 
COAST GUARD DRAWINGS  

 
None.  

 
COAST GUARD PUBLICATIONS  

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements  

OTHER REFERENCES  

None.

3. REQUIREMENTS  

3.1 General. The Contractor must conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability. The requirements of this WI apply to all work under the scope of this contract, whether explicitly stated in all following work items or not, and to all other work subsequently authorized by changes, modifications, or extensions to the contract.  

3.2 Period of Performance. The period of performance for this work is 10MAR2025-28MAY2025 

3.3 Location. The Contractor must perform the work while the USCGC WAESCHE is alongside the pier at U.S. Coast Guard Base Alameda, Coast Guard Island, Alameda CA 94501.   

12314_MLA_1224_418

  1. ITEM 1: Tanks (Potable Water), Clean and Inspect

1.  SCOPE

1.1 Intent.  This work item describes the requirements for the Contractor to clean and inspect the following tank(s):

table 1 - List of tanks

TYPE OF TANK

LOCATION

CAPACITY - 95% (gallons)

Tank Content Disposal
(gallons)

Potable Water

3-68-3-W

5,916

311

Potable Water

3-68-4-W

5,916

311

1.2 Government-furnished property.

None.

2.  REFERENCES

Coast Guard Drawings

Coast Guard Drawing 418A-WMSL-801-001, Rev A, Booklet of General Plans

Coast Guard Drawing 750-WMSL-085-022, Rev B, Tank Sounding and Moment of Inertia Tables (ASC085013B) (WMSL 751) Only

Coast Guard Drawing 750-WMSL-100-37, Rev H, Unit 3120 Structure - 1st Platf to 2nd Dk - Fr 64 to Fr 76 (ASC100312)

Coast Guard Drawing 750-WMSL-167-001, Rev J, Manhole List Installation and Fabrication Details Ship Wide (ASC167001)

Coast Guard Drawing 750-WMSL-530-001, Rev G, Potable Water Systems Diagram (ASC530001)

Coast Guard Drawing 750-WMSL-530-019, Rev E, Potable Water Unit 3120 (ASC530312-PW)

Coast Guard Publications

Commandant Instruction Manual M5100.47 (COMDTINST M5100.47 (series)), Safety and Environmental Health Manual

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2022, Welding and Allied Processes

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022, Requirement for Preservation of Ship Structures

Other References

American National Standards Institute/American Water Works Association (ANSI/AWWA) C652, 2019, Disinfection of Water-Storage Facilities

The Society for Protective Coatings (SSPC) Surface Preparation Specification No.1 (SSPC-SP 1), 2016, Solvent Cleaning

3.  REQUIREMENTS

3.1 General.

 3.1.1 CIR. The Contractor must submit a CIR for the inspections listed in the following paragraph(s):

· 3.7 Inspection

3.1.2 Tech Rep.

None

3.1.3 Protective measures.  The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection).

3.1.4 Interferences.  The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences).  Known interferences include, but are not limited to the following:

  • Fluid contents
  • Piping
  • RO system components
  • Deck grating

NOTE

Coast Guard personnel

Set-Aside: Total Small Business Set-Aside (FAR 19.5) (SBA)

Place of Performance: Alameda, California, UNITED STATES

NAICS Codes:
336611

Files:

Here are other similar opportunities for you